Background: Aerospace Manufacturing Company

Pegasus Manufacturing, Inc. produces complex fuel and oil transport tubing assemblies for jet engines. They manufacture entirely within a 52,000 square foot facility located in Middletown, CT and bring in over $15 million in revenue. The last stage before the machined fittings are welded onto the tube ends is for the parts to be cleaned in an acid bath at Pegagus’ supplier’s (Har-Conn Chrome Co.) facility. The existing process entailed Pegasus shipping the parts to Har-Conn in batches of 50 (to accommodate a minimum lot charge) which Har-Conn then had to unpack and repack in special contamination-proof bag—a labor-intensive and time-consuming effort for the supplier.

Situation: On-Time Delivery Problems with Supplier

  • VISIBILITY: Har-Conn did not have adequate warning from Pegasus of shipments in the pipeline, so when batches arrived they were queued behind other customers’ products to wait their turn for cleaning.
  • URGENCY: Pegasus’s parts were in need of urgent handling since welding is the last step in their production process, so they were always being expedited to customers from Har-Conn—a huge expense.
  • DELIVERY: Pegasus’s delivery performance to its end-customers was unacceptable. They needed CONNSTEP to integrate processes between two both companies to facilitate faster handling of shipments.

Solutions: Supply Chain Optimization with Value Stream Mapping

CONNSTEP implemented a supply-chain approach creating a 2-Tier Value Stream Mapping event together with Pegasus and Har-Conn. Using a current state map, we analyzed the product flow as if there were no boundaries between processes at both companies. Mapping was performed at each of the two locations.

Results:

The project resulted in the following process improvements:

  • Building special boxes to eliminate the need for the individual bags saved Har-Conn 300 man-hours a year of non-value-added work.
  • We established a regular “milk run” for Pegasus to drop off and pick up parts from Har-Conn every Monday, Wednesday and Friday.
  • With better visibility, Har-Conn could reserve capacity for parts coming from Pegasus, who in turn was assured a two-day turn around. Shotgun expediting was eliminated.
  • Har-Conn dropped the minimum-lot charge for individual part numbers and established a fixed price for Pegasus, who agreed to ship a specific aggregate number of parts each time.
  • Costs and excess inventory levels decreased.
  • Flow increased and 100% on-time delivery was achieved.

To learn more about achieving results like these, simply fill out the form on the right of this page ~>

CONNSTEP solved a huge problem for us and helped us bring our delivery rate to 100%. As a direct result of that, we have been awarded with an increase in business which, ultimately, will also benefit (our supplier) Har-Conn.”

CT manufacturer Pegaasus

Chris DePentima

CEO, Pegasus Manufacturing Inc.

“I see great value in the new experiences and perspectives CONNSTEP brings to our business, at reasonable prices. They’re not like consultants, they’re like partners in the business – willing to roll up their sleeves and help.”

AGRussell logo

Mark Burzynski

President, Arthur G Russell Co

“CONNSTEP has proved to be a tremendous resource for ESI. CONNSTEP has helped us to adapt to today’s marketplace and remain a quality minded, competitive global player. Our ISO/TS16949 implementation process was efficient and rewarding. I look forward to our future projects with CONNSTEP.”

esi CT manufacturer

Ron Delfini

President, Engineering Specialties Inc.

“CONNSTEP worked with FuelCell Energy to educate and facilitate Lean initiatives and to help meet our needs to establish an overall production improvement plan. This plan has been utilized over a period of time as a ‘guiding light’ to spur numerous improvements that dramatically reduced our product cost.”

Tom Lucas

Manager, Fuel Cell Energy

“CONNSTEP is a valuable partner to Hologic, providing the expertise and ‘outside eyes’ everyone needs to keep their continuous improvement on track. We are now well-positioned on a dynamic growth path and look forward to a long-term relationship with CONNSTEP.”

Greg Safarik

VP Manufacturing Operations, Hologic

“Our experience working with CONNSTEP has brought us benefits we never expected. It’s a great team to work with!”

Bruce Wheeler

VP of Operations, Metal Finishing Technologies Inc.

“The goals of the team were to reduce manufacturing lead-time, reduce floor space utilized, and increase worker productivity. All the goals were met. CONNSTEP helped us to better compete.”

Tornik CT manufacturer

Dan Rubbo

General Manager, Tornik LLC

“The Business Growth Program is working well for us. We enhanced our website following the meetings to improve our SEO and become more visible to search engines. The segment on negotiating …  promoted changes in our thinking and improved how we interact with customers. The mentoring between sessions was helpful in boosting our progress.”

CT manufacturer Colonial Spring

Bill Lathrop

President, Colonial Spring Co.

Prev Next